The BMW Group is broadening its battery cell base for the Gen6 high-voltage battery. New additions are Samsung SDI for Europe and LG Energy Solution for the USA. This is more than a purchasing decision – it is a hedge against delays, tariffs and political uncertainty.


What it's about

No cells, no Neue Klasse. The 46-millimetre cylindrical cells are the heart of the sixth eDrive generation, so BMW chooses its suppliers carefully. On 9 November 2026 the company announced two additional suppliers: Samsung SDI will contribute cells from European production, while LG Energy Solution (LGES) takes over part of the supply in the USA. Both are due to deliver from the end of the decade – from plants that already exist. No new greenfield factories are needed.


In Europe, the supplier line-up will thus consist of three manufacturers: CATL, EVE Energy and now Samsung SDI. In North America, LGES joins the network.


"Local for Local" – the principle behind it

For years BMW has pursued a strategy of sourcing components wherever possible in the regions where its vehicles are built. The high-voltage battery is a particularly consistent example: Gen6 packs are assembled in five purpose-built plants, each located close to a vehicle plant:

  • Irlbach-Strasskirchen (Lower Bavaria) – for Regensburg, Dingolfing and Munich

  • Debrecen (Hungary) – right next to the new Neue Klasse plant

  • Shenyang (China) – in series production since October 2026

  • Woodruff (South Carolina, USA) – for Spartanburg

  • San Luis Potosí (Mexico)


The logic is simple: the shorter the routes between cell factory, battery assembly and vehicle plant, the lower the risk of supply bottlenecks, transport costs and tariffs. At the same time, BMW does not want to depend on a single supplier per region. That is exactly where the new partnerships come in.


Board member for purchasing Nicolai Martin describes diversification as an integral part of the strategy and stresses that the new contracts are meant to strengthen value creation in Europe and the USA.


Samsung SDI: an old acquaintance returns

For BMW insiders, Samsung SDI is no stranger. The Korean company has supplied cells to Munich since 2009 – starting with the i3 and i8, later also for the iX, i4 and i7. Those were prismatic cells, however. Until now, Samsung SDI had no role as a series supplier for the Neue Klasse.

That is now changing. In Göd, about 25 kilometres north of Budapest, Samsung SDI operates one of Europe's largest battery plants. According to industry reports, equipment for producing 46-millimetre cylindrical cells has been installed there since this summer. Samsung SDI had already produced first sample cells in this format in 2023. Göd is just over 230 kilometres from BMW's battery assembly in Debrecen – practically next door by automotive logistics standards.

Worth noting: Samsung SDI is also an important technology partner for BMW. Since autumn 2025, the two have been working with Solid Power on solid-state batteries, which are already being tested in an i7 test vehicle.


LG Energy Solution: a first for BMW's EVs

With LGES, things are newer. BMW has used the company's cells in hybrid models before, but this is the first time for the brand's fully electric vehicles. The announcement is not a complete surprise, though: in April 2026 LGES reported a major order of more than 100 GWh for 46-series cylindrical cells. Korean media named BMW as the customer at the time – this has not been confirmed to date.


LGES operates several of its own sites in the USA, including Holland and Lansing (Michigan) and Queen Creek (Arizona), the latter designed as a dedicated cylindrical cell plant. The announcement does not say which plant will supply BMW.


Why now? A look at the USA

The announcement carries more weight given the background in North America. Originally, AESC was to supply the cells for battery assembly in Woodruff – from a new plant in Florence County, also in South Carolina. In June 2025, however, AESC paused construction, citing "policy and market uncertainty". BMW said at the time that it would be supplied from AESC's global network during a transitional phase.


With LGES, BMW now gains a second, independent source in the USA that is already producing. Given current US tariff policy and incentives for locally made components, that is a strategically smart move. Incidentally, AESC is not mentioned in the press release.


Europe is no sure thing either

Hungary also shows why broader supplier portfolios make sense. CATL only started trial cell production in Debrecen at the end of September 2026 – well behind schedule. Regulatory measures following wastewater and nickel exposure issues had delayed the start. It is still unclear when series production will begin at the 100 GWh plant. Right next to BMW's Debrecen plant, EVE Energy is building a factory with around 28 GWh of annual capacity, with series production planned for the second half of 2027.


With Samsung SDI, BMW now has a third European supplier that can draw on a site operating since 2017. That site is under scrutiny too, however: there has been a long-running political debate in Hungary about environmental requirements around the Göd plant.


BMW itself points out that building competitive local cell production is extremely complex. It requires high investment, the willingness of global technology leaders to set up locally, and realistic political targets that allow enough time for industrialisation – a clear message to Brussels and Washington.


The know-how stays in Bavaria

Despite the division of labour, BMW develops the cell itself in-house. Three competence centres cover the entire chain:

  • Battery Cell Competence Center (BCCC), Munich: research into new cell chemistries and formats

  • Cell Manufacturing Competence Center (CMCC), Parsdorf: near-series production and testing, focused on quality and resource efficiency

  • Cell Recycling Competence Center (CRCC), Salching: raw material recovery via direct recycling. The centre is operated by Encory GmbH, while the rights to the process belong to BMW.


This expertise is why BMW can use several cell manufacturers in parallel: the specifications come from Munich, and production follows BMW's requirements. According to Hendrik Lang, Head of Purchasing and Quality High-Voltage Batteries, this allows BMW to deal with its partners as equals.


What does the Gen6 cell deliver?

As a reminder: the cylindrical Gen6 cells come in two heights (95 and 120 millimetres) with a uniform diameter of 46 millimetres. Compared with the previous generation, energy density rises by more than 20 percent, while range and charging speed improve by up to 30 percent. The first series model is the BMW iX3, followed by the i3 Sedan and further Neue Klasse derivatives.


The new partnerships are less a technical than a strategic story. BMW is responding to the reality of the battery business: plants start later than planned, projects get paused, and political conditions change faster than production cycles. With five cell suppliers on three continents and its own cell expertise in Bavaria, Munich is spreading its bets – and becoming less dependent on individual partners. For customers, ideally that means one thing above all: stable delivery times for the Neue Klasse.

Meine Blog Artikel erstelle ich aus folgenden Quellen und Hilfsmittel:

Quellen: BMW Press Group, Google, Instagram, Erfahrungen aus dem Auto Gewerbe

Hilfsmittel: Für die Grammatik der Texte nutze ich Google Gemini und Claude

Comments


BMWNewsBlog.com

  • Instagram

Legal notice Private BMW fan blog

© 2026 BMWNewsBlog.com

Contact
bottom of page